Permit Comment & Soil Report Review

City Rejected Your Soil Report in Ontario?

If a municipality rejected, questioned, or did not accept your soil report, the next step is not to guess. The issue may be simple clarification, or it may mean the report does not address the proposed construction, bearing capacity, foundation recommendations, groundwater, fill, retaining walls, or other site-specific conditions.

This guide explains why cities reject or question soil reports, what the reviewer may actually be asking for, and when you may need a geotechnical review, response letter, supplemental investigation, or new soil report.

Permit Comment Review Soil Report Second Opinion Foundation & Bearing Capacity Issues

Request Report Review Call 416-822-6643

Quick Answer

If the city rejected or questioned your soil report, read the exact permit comment carefully. Common reasons include missing bearing capacity recommendations, an outdated or reused report, boreholes that do not cover the proposed work, lack of groundwater or fill discussion, unclear foundation recommendations, or a report that does not match the submitted drawings.

If you already have a report and city comment, start with our Soil Report Review in Ontario service.

What Does It Mean When the City Rejects a Soil Report?

In many cases, the city is not “rejecting” the soil report in the way people imagine. The reviewer may be saying that the submitted information does not answer the permit question, does not match the drawings, does not include a required recommendation, or does not give enough site-specific support for the proposed work.

The municipal comment may use wording such as:

The key is to identify what the reviewer actually needs. A short comment can represent a narrow clarification request or a broader geotechnical issue.

Do not respond blindly

Before replying to the city, compare the exact comment with the report and drawings. A weak or incomplete response can create another round of comments and more delay.

Get the Comment Reviewed

Common Reasons a Soil Report Is Rejected or Questioned

1. The Report Does Not Match the Current Drawings

A soil report may have been prepared for an earlier design, a different foundation layout, a different building footprint, or a previous version of the project. If the submitted drawings changed after the geotechnical investigation, the reviewer may question whether the report still applies.

This is common when projects evolve from a simple addition into a larger renovation, underpinning project, basement lowering, retaining wall design, garden suite, or full replacement dwelling.

2. Bearing Capacity Is Missing or Unclear

Many permit comments relate to footing support. The city or structural engineer may need an allowable bearing pressure or confirmation that the proposed footings are supported by suitable soil conditions.

If the report does not clearly provide bearing capacity recommendations, or if the recommendation is not tied to the proposed footing level, the reviewer may ask for clarification.

Related page: Soil Bearing Capacity Testing in Ontario

3. Boreholes Do Not Cover the Proposed Work Area

A report may include boreholes, but they may not be located near the proposed foundation, addition, retaining wall, underpinning zone, or new structure. If the investigation area does not represent the actual construction area, the city may question whether the recommendations are applicable.

4. The Report Is Too Old or Was Prepared for Another Purpose

Old geotechnical reports can sometimes be helpful, but they are not automatically acceptable for a new permit. Site conditions may have changed, the proposed work may be different, or the report may lack the recommendations now required.

Related guide: Can a Soil Report Be Reused in Ontario?

5. Groundwater, Fill, or Soft Soil Was Not Addressed

If the site has fill, organic material, soft soil, high groundwater, poor drainage, or wet excavation conditions, the reviewer may need more than a basic bearing value. The report may need to discuss construction implications, drainage, unsuitable material, or foundation recommendations.

6. Retaining Wall or Slope Issues Were Not Covered

Retaining walls and sloped sites often require geotechnical input beyond simple bearing capacity. The reviewer may need earth pressure parameters, backfill recommendations, drainage notes, global stability comments, or foundation support recommendations.

Related guide: Soil Report for Retaining Wall in Ontario

7. The Report Does Not Respond to the Exact City Comment

Sometimes the report is technically detailed but still does not answer the reviewer’s specific question. A city may request confirmation of one issue, while the submitted report discusses general soil conditions without clearly connecting the recommendations to the permit drawings.

What Should You Do First?

The first step is to slow down and organize the information. Do not assume the entire report is useless, and do not assume new drilling is automatically required. The correct next step depends on the exact comment and the reason the report was not accepted.

Start by gathering:

Once the documents are together, compare the reviewer’s comment against the report. The issue may be missing information, unclear wording, outdated scope, insufficient investigation, or mismatch between report and drawings.

When a Clarification Letter May Be Enough

A rejected or questioned soil report does not always mean the site needs new fieldwork. In some cases, the original geotechnical engineer may be able to issue a clarification letter, addendum, or response to the city.

Clarification may be enough when:

However, if the report does not cover the relevant area, lacks required data, or does not address current site conditions, clarification alone may not be enough.

When a Second Opinion or Report Review Makes Sense

A second opinion can help when you are unsure whether the city’s comment is valid, whether the report is missing something, whether the issue can be resolved with clarification, or whether new testing is likely required.

A review may help determine:

Related page: Soil Report Review in Ontario

When New Soil Testing May Be Required

New testing may be required if the existing report cannot reasonably support the current permit submission. This is more likely where the proposed work is different from the original report scope or where the report lacks site-specific data for the relevant area.

New or supplemental investigation may be needed when:

If the issue relates to permit approval, see Soil Testing for Building Permit in Ontario.

How to Respond to the City Without Creating More Delay

A strong response should directly address the reviewer’s comment. Avoid sending a generic explanation or resubmitting the same report without clarifying why it answers the comment.

A better response strategy usually includes:

  1. Identify the exact issue: bearing capacity, scope, groundwater, fill, retaining wall, old report, or mismatch with drawings.
  2. Confirm whether the current report answers it: do not assume; check the report against the drawings.
  3. Contact the original engineer if appropriate: clarification from the author may be required.
  4. Request independent review if uncertain: especially where cost, delay, or disagreement is involved.
  5. Submit a targeted response: address the comment directly with the required information.

The objective is not to overwhelm the reviewer. The objective is to give them the specific geotechnical information they need to continue the permit review.

Need help deciding the next step?

Send the report, city comment, and drawings. We can review whether the issue appears to require clarification, a second opinion, supplemental investigation, or a new report.

Request Soil Report Review

City Rejection vs. Structural Engineer Concern

Sometimes the concern does not come directly from the city. A structural engineer may question whether the report provides enough information for the foundation design. This can still affect the permit because the structural design may depend on geotechnical recommendations.

Structural concerns may involve:

Related guide: Soil Report vs. Structural Engineer Report

Can You Submit the Same Soil Report Again?

Resubmitting the same report without clarification is risky. If the reviewer already said the report is insufficient, another submission of the same document may create the same result unless the response explains exactly where and how the report addresses the comment.

Resubmission may work only if:

Otherwise, a clarification letter, addendum, supplemental fieldwork, or new report may be a better path.

How Much Can a Rejected Soil Report Cost You?

The cost is not only the review fee or the cost of additional testing. The bigger cost can be delay. Permit comments can affect design schedules, contractor start dates, financing timelines, material pricing, and construction coordination.

Costs may include:

For pricing context, see Soil Report Cost in Ontario and Geotechnical Investigation Costs in Ontario.

Related Resources

Need Help With a Rejected Soil Report?

Send us the soil report, city comment, drawings, and your specific concern. We can review whether the issue appears to require clarification, supplemental information, a second opinion, or updated geotechnical work.

Request Soil Report Review


Frequently Asked Questions

Why would a city reject a soil report?

A city may reject or question a soil report if it does not address the proposed work, lacks bearing capacity or foundation recommendations, does not match the drawings, is outdated, has insufficient borehole coverage, does not address groundwater or fill, or fails to respond to the reviewer’s specific comment.

What should I do if the city rejects my soil report?

Start by reviewing the exact municipal comment. Then compare it with the report, drawings, and project scope. The next step may be clarification from the original engineer, a geotechnical review, a response letter, supplemental fieldwork, or a new soil report.

Can a second opinion help if my soil report was rejected?

Yes. A second opinion can help identify whether the report addresses the city comment, whether information is missing, whether the issue is wording or scope, and whether clarification, supplemental investigation, or a new report is likely required.

Does a rejected soil report always mean I need new testing?

No. Sometimes the report may only need clarification, a response letter, or confirmation that the recommendations apply to the submitted drawings. New testing may be required if the report does not cover the relevant area, is outdated, lacks required recommendations, or does not address site-specific conditions.

Can a rejected soil report delay my building permit?

Yes. If the city requires clarification or additional geotechnical information, the permit review may be paused until the issue is addressed. A targeted response can help reduce back-and-forth and avoid further delay.